Repairs of the water pipeline and the water supply tower in Fedorivka, Odesa Region, is ongoing as part of the LDS project supported by the Church of Jesus Christ of Latter-Day Saints. The village population is 150 households, and the access to water is the urgent need among the villagers. Currently, the water supply pipe routing works are in progress. On July 12th, ADRA Ukraine engineers travelled on site to conduct technical supervision, verify the pipe routing depth and check the connection point and feed lines to the households.

The next step according to the design plan is to install concrete turnarounds for the water pipeline in Fedorivka. Meanwhile, repair welding works are in progress at the water tower site, and foundation laying is upcoming.